- The repair operations are underway with the repair crew (22 personnel) all on board the repair vessel.
- Ice conditions remain favorable around the area of operation. Vessel is positioned east of the cable line in 25M of water.
- Wind conditions are somewhat challenging, but repair work is advancing.
- Visibility at the cable location is zero which is not surprising based on shallow water and gale force winds stirring up the water column.
- Developing an ROV excavation plan, also developing a grapnel recovery plan B.
- Nome and Oliktok Point cable landing stations manned by Quintillion Tech/Eng personnel to support repair and restoral of service.
- Estimates on repair duration and service restoration will be forthcoming.