Recent Activity

  1. The repair operations are underway with the repair crew (22 personnel) all on board the repair vessel.
  2. Ice conditions remain favorable around the area of operation. Vessel is positioned east of the cable line in 25M of water.
  3. Wind conditions are somewhat challenging, but repair work is advancing.
  4. Visibility at the cable location is zero which is not surprising based on shallow water and gale force winds stirring up the water column.
  5. Developing an ROV excavation plan, also developing a grapnel recovery plan B.
  6. Nome and Oliktok Point cable landing stations manned by Quintillion Tech/Eng personnel to support repair and restoral of service.
  7. Estimates on repair duration and service restoration will be forthcoming.